Friday, May 27, 2016

Waiting on Approvals to Make Final Connection along Sunset Ridge Road

Work Completed Last Week, May 23rd to May 27th
·         No work completed on-site
·         Continuing to wait for AT&T to complete work on-site
·         Waiting for required approvals to make final connection along Sunset Ridge Road

 Work Anticipated to be completed Next week, May 30th to June 3rd
·         Waiting on necessary approvals prior to making final water main connection at Sunset Ridge Road and Maple Lane

We are continuing to wait for approvals to make the final water main connection along Sunset Ridge Road. Once the approvals are received, the remaining underground utility work will be scheduled as quickly as possible. Once the underground utilities are completed, the roadway rehabilitation and landscape restoration phases of the project will begin.

Thanks again for all your patience and understanding.