Friday, June 17, 2016

Roadway Improvements On-Going

Work Completed Last Week, June 13th to June 17th
·         Roadway excavation
·         Widening of pavement around various corners to allow for easier turning movements
·         Removal of existing roadway surface in preparation for new asphalt pavement
·         Grading of existing base materials in preparation for new asphalt pavement
·         Performing base repairs in areas where the existing materials were unsuitable.
·         Repair existing water main along Sunset Ridge Road that was identified during water main connection.
·         Paving of the first layer of asphalt pavement scheduled for Saturday, June 18th

Work Anticipated to be completed Next week, June 20th to June 24th
·         Perform final testing of new water main
·         Internal televising of storm sewer and sanitary sewer
·         Grading of existing landscape
·         Installation and final grading of topsoil
·         Sod installation in areas disturbed during construction

The first layer of asphalt pavement is scheduled to be installed on Saturday, June 18th. This will be a major project milestone as a smooth driving surface will be re-established. Once the first layer of asphalt is installed, the contractor will complete the final inspections and tests for the storm sewer, sanitary sewer, and water main.

The contractor is also anticipating to begin the landscape restoration later next week. As the landscape restoration is completed, the project will be closer to being finalized and your landscape areas will begin to look the way they did prior to the construction project.

Thanks again for all your patience and understanding through the construction progress. Hopefully with the upcoming asphalt pavement installation and landscape restoration, you will begin to see what the final project will look like.

Friday, June 10, 2016

Final Water Main Connection at Sunset Ridge Road Completed.

Work Completed Last Week, June 6th to June 10th  
·         Received required approvals to make connection to existing water main along Maple Lane at Sunset Ridge Road
·         Make connection to existing water main at Maple Lane and Sunset Ridge Road.

Work Anticipated to be completed Next week, June 13th to June 17th
·         Roadway excavation were required
·         Widening of pavement around various corners to allow for easier turning movements.
·         Removal of existing roadway surface in preparation for new asphalt pavement
·         Grading existing base materials in preparation for new asphalt pavement
·         Paving 1st layer of asphalt pavement.

The required approvals to make the final connection were finally received this week. The contractor began scheduling the final water main connection as soon as the approvals were received. The final water main connection was completed on Friday.

The underground utility improvements are now completed with the exception of a few minor items that need to be addressed.

Next week the contractor will begin the roadway improvement phase of the project. It is anticipated the first layer of asphalt pavement will be installed either later in the week or early the following week. Once the asphalt pavement is installed, a major project milestone will be reached. This will greatly reduce the amount of dust along the project site and provide a smooth driving surface.

During the roadway improvement phase of the project, travelling along Glen Oak Drive and Maple Lane will be increasingly more difficult due to the number of large pieces of equipment along the roadway. Please use caution or alternates routes if possible.

Thank you again for all your patience due to the extended foreseen delay waiting of approval to make the final water main connection along Sunset Ridge Road. Your patience and understanding has been greatly appreciated. The Village and contractor will do everything possible to get the project completed as quickly as possible moving forward.

Friday, June 3, 2016

Waiting on Approval to Work at Sunset Ridge Road. Roadway Improvements to Begin

Work Completed Last Week, May 30th to June 3rd
·         No work completed on-site
·         Waiting for required approvals to make final connection along Sunset Ridge Road

Work Anticipated to be completed Next week, June 6th to June 10th
·         Removing the existing asphalt surface in preparation for installing new asphalt surface
·         Excavation and base installation for roadway widening in a few areas.
·         Waiting on necessary approvals prior to making final water main connection at Sunset Ridge Road and Maple Lane

We have made continued attempts to receive the required approvals to complete the final water main connection at Maple Lane and Sunset Ridge Road. Please understand the Village is doing everything possible to get the project completed in a timely manner. We understand the frustration living within a construction zone with limited or no construction activity on-going.

Since the approvals are taking substantially longer than anticipated, the contractor will being the roadway improvement prior to getting the required approvals to make the connection at Sunset Ridge Road and Maple Lane.

Thanks again for all your patience and understanding during these unforeseen delays.

Friday, May 27, 2016

Waiting on Approvals to Make Final Connection along Sunset Ridge Road

Work Completed Last Week, May 23rd to May 27th
·         No work completed on-site
·         Continuing to wait for AT&T to complete work on-site
·         Waiting for required approvals to make final connection along Sunset Ridge Road

 Work Anticipated to be completed Next week, May 30th to June 3rd
·         Waiting on necessary approvals prior to making final water main connection at Sunset Ridge Road and Maple Lane

We are continuing to wait for approvals to make the final water main connection along Sunset Ridge Road. Once the approvals are received, the remaining underground utility work will be scheduled as quickly as possible. Once the underground utilities are completed, the roadway rehabilitation and landscape restoration phases of the project will begin.

Thanks again for all your patience and understanding.

Have a fun and safe Memorial Day Weekend!!!

Monday, May 23, 2016

Majority of Underground Utility Improvements Completed

Work Completed Last Week, May 16th to May 20th  
·         Connection between existing water main and new water main at Maple Lane and Glen Oak Drive
·         Completed storm sewer installation
·         Completed storm sewer service installation
·         Completed water service replacements
·         Began abandoning old fire hydrants and valve vaults
·         AT&T continued with utility line relocation and replacement.
·         General site clean-up

Work Anticipated to be completed Next week, May 23rd to May 27th  
·         Waiting on necessary approvals prior to making final water main connection at Sunset Ridge and Maple Lane
·         Perform walk-through with AT&T to ensure work is completed.

The underground utility work being performed under the Village of Glenview contract is nearly completed, with the exception of the final connection near Sunset Ridge and Maple Lane. Once the underground work and AT&T work is completed, the roadway rehabilitation and landscape restoration phases of the project will begin.

Thanks again for all your patience and understanding.

Friday, May 13, 2016

AT&T Working On-Site


Work Completed Last Week, May 9th to 13th
·         Continued with water service replacements
·         AT&T on-site replacing and relocating utility lines

Work Anticipated to be completed Next week, May 16th to May 20th  
·         Connection between existing water main and new water main at Maple Lane and Glen Oak Drive scheduled for Monday, May 16th
·         Abandon old valve vaults and fire hydrants.
·         AT&T contractor to complete utility line relocations and replacements

AT&T is continuing to relocated and install new utility lines along the project site. This work is anticipated to be completed near the middle to end of next week. Once AT&T has completed their work, the Village’s contractor will return to complete the remaining work.  

Thank you for your patience and understanding while AT&T completes their work.

 

Friday, May 6, 2016

AT&T to Begin Utility Line Replacement and Relocation.

Work Completed Last Week, May 2nd to May 6th  
·         Continued with storm sewer mainline installation
·         Continued with storm sewer service installations to individual homes
·         Grind-in-place asphalt
·         Sanitary sewer service replacements
·         Received required approvals to place new water main into service
·         Started water service replacements

Work Anticipated to be completed Next week, May 9th to May 13th
·         Complete water service replacements
·         AT&T contractor on-site replacing and relocating utility lines

Water service replacements will continue, and hopefully be completed, along Maple Lane next week. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 1 to 2 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

AT&T is anticipated to be on-site next week beginning utility line replacement and relocation. It is anticipated this work will take approximately 2 weeks to complete. During this time, the contractor hired by the Village to construct the public improvements will not be on-site performing work. With the narrow roadways and limited space to work, it would not be advantageous to have both contractors working at the same time.  The Village will monitor the schedule and progress of the AT&T contractor. As soon as they are completed with their improvements, the Village improvements will begin again.

Thank you for your patience and understanding during this transition between the AT&T work being completed and the Village project being placed on hold for the time being.