·
Received required approvals to make connection
to existing water main along Maple Lane at Sunset Ridge Road
·
Make connection to existing water main at Maple
Lane and Sunset Ridge Road.
Work Anticipated to be completed Next week, June 13th
to June 17th
·
Roadway excavation were required
·
Widening of pavement around various corners to
allow for easier turning movements.
·
Removal of existing roadway surface in
preparation for new asphalt pavement
·
Grading existing base materials in preparation
for new asphalt pavement
·
Paving 1st layer of asphalt pavement.
The required approvals to
make the final connection were finally received this week. The contractor began
scheduling the final water main connection as soon as the approvals were
received. The final water main connection was completed on Friday.
The underground utility
improvements are now completed with the exception of a few minor items that
need to be addressed.
Next week the contractor will
begin the roadway improvement phase of the project. It is anticipated the first
layer of asphalt pavement will be installed either later in the week or early
the following week. Once the asphalt pavement is installed, a major project
milestone will be reached. This will greatly reduce the amount of dust along
the project site and provide a smooth driving surface.
During the roadway
improvement phase of the project, travelling along Glen Oak Drive and Maple
Lane will be increasingly more difficult due to the number of large pieces of
equipment along the roadway. Please use caution or alternates routes if
possible.
Thank you again for all your
patience due to the extended foreseen delay waiting of approval to make the
final water main connection along Sunset Ridge Road. Your patience and
understanding has been greatly appreciated. The Village and contractor will do
everything possible to get the project completed as quickly as possible moving
forward.