·
Roadway excavation
·
Widening of pavement around various corners to
allow for easier turning movements
·
Removal of existing roadway surface in
preparation for new asphalt pavement
·
Grading of existing base materials in
preparation for new asphalt pavement
·
Performing base repairs in areas where the
existing materials were unsuitable.
·
Repair existing water main along Sunset Ridge
Road that was identified during water main connection.
·
Paving of the first layer of asphalt pavement
scheduled for Saturday, June 18th
Work Anticipated to be completed Next week, June 20th
to June 24th
·
Perform final testing of new water main
·
Internal televising of storm sewer and sanitary
sewer
·
Grading of existing landscape
·
Installation and final grading of topsoil
·
Sod installation in areas disturbed during
construction
The first layer of asphalt pavement is scheduled to be installed on Saturday, June 18th. This will be a major project milestone as a smooth driving surface will be re-established. Once the first layer of asphalt is installed, the contractor will complete the final inspections and tests for the storm sewer, sanitary sewer, and water main.
The contractor is also
anticipating to begin the landscape restoration later next week. As the
landscape restoration is completed, the project will be closer to being
finalized and your landscape areas will begin to look the way they did prior to
the construction project.
Thanks again for all your
patience and understanding through the construction progress. Hopefully with
the upcoming asphalt pavement installation and landscape restoration, you will
begin to see what the final project will look like.