Friday, May 13, 2016

AT&T Working On-Site


Work Completed Last Week, May 9th to 13th
·         Continued with water service replacements
·         AT&T on-site replacing and relocating utility lines

Work Anticipated to be completed Next week, May 16th to May 20th  
·         Connection between existing water main and new water main at Maple Lane and Glen Oak Drive scheduled for Monday, May 16th
·         Abandon old valve vaults and fire hydrants.
·         AT&T contractor to complete utility line relocations and replacements

AT&T is continuing to relocated and install new utility lines along the project site. This work is anticipated to be completed near the middle to end of next week. Once AT&T has completed their work, the Village’s contractor will return to complete the remaining work.  

Thank you for your patience and understanding while AT&T completes their work.