Limited work completed on-site
·
Internal televising of storm sewer and sanitary
sewer
·
Patching of roadway at Sunset Ridge Road and
Maple Lane
·
General
site clean-up
Work Anticipated to be completed Next week, July 4th
to July 8th
·
No work over the July 4th Holiday
·
Installation and final grading of topsoil
The contractor is scheduled
to begin grading and installing topsoil next week.
The sod installation and
asphalt driveway restorations will be performed following the paving of the
final asphalt surface. Currently the asphalt surface paving is scheduled of the
week of July 11th.
The contractor will not be
on-site over the July 4th Holiday. Have a safe and enjoyable Holiday
Weekend!!!