·
Rough grading of areas to be landscaped
·
Installation and grading of topsoil
·
Tree replacement on Glen Oak
·
Adjusting structures to final grade
·
Performed final testing for underground utility
improvements
·
Performed internal televising of sewers
·
Performed walk-through with Village staff to
find any items that needed additional work
·
Made minor repairs at locations identified by
Village staff
·
General site clean-up
Work Anticipated to be completed Next week, July 18th
to July 22nd
·
Asphalt surfacing paving
·
Asphalt driveway restoration
·
Sod installation, weather dependent
Paving of the asphalt surface
layer is scheduled for next week. Additional information will be provided when
the schedule is finalized regarding travel cautions and restrictions during the
paving operations and prior when the existing asphalt will have a thin layer of
oil sprayed on it. Following the asphalt surface paving, the landscape
restoration with sod and asphalt driveway restorations will be completed. The
reason these final restorations will be completed following the asphalt paving
is so the final grades will match the newly paved surface.
The contractor has completed
the installation and grading of topsoil in those areas disturbed during
construction. The timing of the sod installation is still being discussed. Due
to the hot weather and lack of rain the past few weeks, this is not the optimum
time for sod. If installation is delayed to a time with more favorable growing
conditions, we will keep you posted regarding when the sod installation will
occur. Our goal is to ensure a healthy stand of grass is established.
Thanks again for all your
patience and the end of the project is near!!!!