Monday, April 25, 2016

Water Main On-Going

Work Completed Last Week, April 18th to April 22nd
·         Layout of Right-of-Way Limits
·         Made connection to existing water main at Glen Oak Drive and Linden Lane
·         Directional drilling of water main along Maple Lane
·         Directional drilling of water main along Glen Oak Drive

Work Anticipated to be completed Next week, April 25th to April 29th
·         Open cut water main installation
·         Installation of valves and fire hydrants
·         Begin required testing of new water main prior to placing into service.
·         Begin storm sewer installation.

Thank you for all your patience as the heavy construction as started. We understand the inconveniences you are experiencing with the water main shut-downs and the difficulty getting around your neighborhood with the large construction equipment. Please understand we will do everything possible to make these delays as minimal as possible.