Resident Preconstruction Meeting conducted on
Thursday, April 14th.
·
Construction lay-out of improvements
·
Internal televising of existing storm and
sanitary sewer systems.
Work Anticipated to be completed Next week, April 18th
to 22nd
·
Layout of existing right-of-way limits
·
Exploratory excavation of existing utilities
·
Begin water main installation via directional
drilling methods
·
Begin storm sewer installation